Methow
Valley Collaborative Action Team
Tripod Post Fire Salvage
Jim
Doran, J.D., IBDR
Community
Forestry Resources
(ph)
509-997-2295
(cell) 509-293-1535
(fax) 509-997-2192
Tripod Post
Fire Salvage in the Methow Valley District
Collaborative Action Team Report –
October 27, 2006
Various discussions, a meeting, and a field trip to the
Tripod Fire site have led to the following questions, conclusions and
suggestions from the Collaborative Action Team (CAT) regarding the timely
salvage of materials from the Methow District of the fire. The CAT is also interested in salvage
opportunities on the Tonasket District, including several small research
projects, and will be providing input in the near future.
The Tripod Salvage Collaborative Action Team (CAT) is comprised
of a group of individuals and organizations with diverse interests working
informally with the U.S. Forest Service to implement economically and
environmentally viable salvage logging activities in response to the 2006
Tripod Fire. The CAT is open to all interested persons and currently
includes representatives from American Forest Resource Council, The Wilderness
Society, Vaagen Brothers Lumber Company, Conservation Northwest, Boise Cascade,
Washington Department of Fish and Wildlife, The Lands Council, Okanogan
Conservation District, and the local community.
The Provincial Advisory Committee (PAC) has agreed that
salvage should be focused in the dry and mesic forest, and attempt to be both economically
viable and to also restore the stand structure and fuel loading towards the
historic range of variability where salvage is done. The CAT concurs with this commitment.
1. Timeliness is the governing issue.
It is recognized that the burned stands are in urgent need of treatment
as soon as possible in order to capture the value that will soon be lost. Foresters
demonstrated the existing infiltration of bugs and fungus already hitting the
trees that burned in August. The merchantable
Òshelf lifeÓ of the standing Ponderosa Pine (of all size classes) and the small
diameter (12Ó and smaller) fir, spruce and lodgepole pine will reach its limit
by the end of April, 2007. Large
diameter (12Ó and larger) Douglas fir and spruce may last until the first of
August depending on the weather.
This may vary slightly depending on the aspect of any particular
stand. After March, 2007 the value
of any sale offered will be in the state of reduction due to the deterioration
of the material.
The project analysis team is currently preparing field maps,
unit descriptions and treatment proposals. If the analysis is fully funded, the field work and
implementation guidelines can be ready prior to the end of the NEPA permit
process in any of the following scenarios.
a. According to the Forest Service timeline,
if the NEPA preparation of this project is done on the EIS timeline the award
dates fall beyond a true salvage deadline; i.e., end of June 2007 through an
emergency determination EIS or September 2007 without an emergency
determination. Both cases will very
likely result in a failed salvage project.
b. If NEPA is done through an EA without an
emergency determination the award date is projected to be the end of June, 2007
and the project will likely fail.
c. If an emergency determination is given
for an EA, the projected award date is mid-March 2007. The emergency determination timeline
could be reduced from 105 days to 68 days if sufficient manpower were
applied. This could conceivably
have a project award date in late January 2007 if the NEPA process was begun in
the first week of November, 2006.
d. * The most aggressive timeline with an
emergency situation determination under an EA could be as follows:
a) Scoping letter send out and first publication
on November 1, 2006
b) Scoping period ends on December 1, 2006.
c) EA issued on December 4, 2006 with 30
days comment period.
d) Public comment period closes on January 4,
2007.
e) Respond to comments and agency
consultations to January 10, 2007.
f) Decision Notice and FONSI signed and
legal ad begins to run on January 10, 2007.
g) Advertisement period ends on January 24
2006.
h) Bids opened on January 25, 2006.
i) Contract awarded on January 26, 2006.
*Note:
Several of these tasks can be done simultaneously. The Forest
Service Enterprise Team may be utilized to assist in this expedited timeline.
This timeline, above, is based upon the Wenatchee-Okanogan
Forest projection of the legal comment period beginning on December 1,
2006. This requires a scoping
letter to be disseminated on November 1, 2006. This does not suggest an earlier Òstarting pointÓ, only that
the process can be completed expeditiously within the framework of existing
laws.
The Wilderness Society has voiced concerns about the use of
emergency determination for economic purposes alone but is committed to this
collaborative process.
US Fish & Wildlife and NMFS are key participants in the
determination of non-significance for an EA, as well as consultation under the
ESA. The Wenatchee-Okanogan Forest
has a close working relationship with these agencies and it is expected that informal
consultation could be completed before January 2007.
Funding and personnel for the project analysis and project
preparation and for the NEPA process are potential limiting factors. The CAT could act to assist in the
acquisition of funding in coordination with the Wenatchee-Okanogan Forest.
2. What acreage can be salvaged: The Methow side of the fire has been initially determined to
hold approximately 36,000 acres of potential salvage stands. This has been reduced considerably
because of various reasons to a potential acreage of 22,000. The preliminary analysis shows the
following treatment categories per acreage:
There is substantial likelihood that
more acres will Òfall outÓ of the project as units are described. For instance, the helicopter units
may likely be financially impractical.
At todayÕs date the Okanogan-Wenatchee Forest has determined that out
of these analysis acres, there will likely emerge salvage opportunities on
7,000 acres with 75% as ground based systems and 25% as skyline systems. 7,000 acres amounts to 4% of the
acreage within the burned area. The most optimal stands are being laid out
for salvage while the interspersed live and dead stands are being dropped
due to time and expense that will render them economically non-viable. A ball-park volume estimate is 25mmbf
to 60mmbf assuming yield of 12mbf-20mbf per acre on the acres actually
salvaged. A Òweight scaleÓ sale
could also adjust the acreage up or down due to on-site conditions as the
project is implemented.
3. What trees can be salvaged: The Forest Service intends to use the Scott Guidelines
for mortality will be used to determine which trees have suffered mortal
damage. There remains a
question regarding the salvage of trees over 21Ó dbh, relative to each
species, as well as the proportion of snags in each size class to be left in
the stand. Trees over 24Ó to 25Ó,
except for Ponderosa Pine, are too large for local processing and could be
left as snags. Further
discussion is needed regarding salvage and retention of large Ponderosa
Pine.
4. Inventoried Roadless Areas and proposed roadless areas:
The Forest Service has removed all of the roadless or proposed
roadless areas from the initial proposals. Logging of any of these roadless areas would be
controversial and should be avoided.
5. Weight Scale: The use of weight scale will improve the project
preparation timeline, will give more flexibility to the Òon the groundÓ
implementation of the salvage work and will increase the viability of the
economics of the project (i.e., will anyone buy the sale?). Weight scale should be combined with
optional removal due to deterioration so that spoiled trees do not have to
be removed.
6. The Ògreen treeÓ program: The
Tripod Salvage project will distract all personnel and funding from the
three currently planned fuels reduction projects in the Methow District,
based on currently available funding.
This is an untenable situation to the CAT since it shifts the focus
of the agencyÕs work to salvage and away from prevention or preparation for
non-catastrophic fires. This is
an issue needing immediate agency attention. It has been suggested that the revenues from this Tripod
salvage Project be retained by the local Forest to be applied to its Ògreen
treeÓ program.
Note:
If the Tripod Salvage project is not funded and staffed adequately or
if the NEPA timeline is prolonged and the project fails, then both the salvage
and the Ògreen treeÓ programs will be squandered for at least 2007. This is an unacceptable situation to
place the local Forest in.
The CAT can assist the Forest Service
in the acquisition of funding to promptly move this salvage project forward
and to continue the preparation of the regular ÒgreenÓ projects that have
been interrupted by this large-scale fire. The CAT members can also assist with an outreach effort
with other organizations for purposes of promoting the goals and objectives
stated herein.