Timeline For the
Project – Panhandle Forest Coalition
TASK
DATES RESPONSIBILITY OTHER PARTICIPANTS
1. Project
Administration Chamber Committee Facilitator
6/1/05
- continuing
2. Coalition
Board Meetings Facilitator Chamber
Committee
6/1/05
- continuing Coalition
Participants
3. USFS
Project Planning Facilitator
Participants
9/1/05 – continuing Technical Assistance
4. Group Retreat Facilitator Participants
6/1/05 Technical Assistance
5. Community
Meetings Chamber
Committee Participants
6/1/05
– continuing Facilitator
6. Organize
Project Team Facilitator
Participants
12/1/05
Technical
Assistance Chamber
Committee
7. Media
Exposure Chamber
Committee
6/1/05
- continuing Facilitator Participants
8. Board
Formation Facilitator Participants
8/1/05
9. Educational
Forums Facilitator Chamber
Committee
8/1/05-
continuing Technical
Assistance Participants
10. Board Training
9/1/05 Technical
Assistance Board
members
11. Evaluate
Project Chamber
Committee Facilitator
1/1/06
Board
of Coalition
12. Reports to NFF Board of Coalition Facilitator